Why did that street get fixed and not mine? San Antonio has an answer, and it is more a formula than a favor.
The city’s budget for the Street Maintenance Program in fiscal year 2027 is $129.8 million, according to a memo in the Oct. 15, 2026 City Council A Session packet. The memo came with item 11 on the consent agenda: a task order contract with J&P Paving Co., Inc. for the 2027 Street Rehabilitation Package 2, in an amount not to exceed $9,017,077.
How the money is divided
The memo describes two pots. Mira, here is the split:
- $103.3 million is “allocated 100% based on street condition per Council District.” Worse pavement, bigger share.
- $26.5 million, funded in the 2022 Bond, is allocated half on the size of each district’s street network and half on street condition.

The two add up to the $129.8 million. The memo also says $15.3 million of that is in-house work and $114.5 million is contracted out, which is where a package like this one comes in.
What this contract pays for
The memo says the program takes a two-pronged approach, pavement preservation and pavement rehabilitation, and that this contract covers rehabilitation: repairs to the street’s base structure, the asphalt surface overlay, wheelchair ramp improvements and any other required work. Because it is a task order contract, Public Works can use it for several projects over time instead of bidding each one separately. The memo says that is meant to speed up delivery.
SAWS will reimburse $253,025 and CPS Energy $18,750 of the total, which is $271,775 between them. The rest comes from the General Fund, the Advanced Transportation District Fund, the Right of Way Fund and the Bond Program, all included in the FY 2027 Capital Budget.
How the contractor was chosen
The project was advertised starting June 29, 2026. Bids opened Aug. 11, 2026, and eight bids came in that were judged responsive. J&P Paving submitted the lowest one. The memo adds that the city set an 8% small business contracting goal and that J&P is a certified small business that committed to meet it by doing the work itself.
What we don’t know yet
The packet does not list which streets this contract will repair, so I can’t tell you whether yours is on it. It also does not show how Council voted on Oct. 15, and I could not find readable minutes, so this describes the item as proposed. The memo says the work is citywide; the street-by-street list is a question for Public Works and your council office.
Now go check your street, mija. Then ask your council member what is on the list.